1. Rubble soling rate analysis: (Rate Analysis for Rubble soling)

The rate analysis for rubble soling is mainly depend on the material required and the cost of material, labour, equipment etc.

The material needed for the complete activity for Rubble soling rate analysis,

  1. Rubble soling: Here we are considering the rubble soling of any size. The important factor here to consider here is the dressing. The dressing wastage considered is 10% . This percentage is again depend upon the size and shape of the rubble. For elongated and completely uneven shape the dressing wastage can be upto 20%.
  2. Murum: For murum compaction is must, as it is going to be used in plinth feeling. Here in the sample calculation compaction is not considered.

Rubble soling rate analysis is as follows,

Item Details: Rubble soling 230mm thick with murum blinding coarse

Quantity Assumed: 10cu-m

Rate Assumed: (please note that the rate may varies depending upon the location and time)

  • Rubble: 530 Rs per cum
  • Murum: 425 Rs per Cum
  • Labour charges: 530Rs per Cum
Item No.ItemExplainationQuantityUnitRate/unitAmount
AMaterial     
1Rubble10 cum + 1cum11cum5305830
  (Add 10% dressing of the stone)    
2Murum2cum2cum425850
 (50mm loose murum layered over rubble soling for filling the same into soling gaps)10cum x 2%    
 Total of A    6680
BLabour charges 10no5305300
CWastage @ 5%    334
DPlant & machinery @ 1%    66.8
EWater & electricity including curing @ 2%    133.6
 Total    12514.4
FAdd for profit & Overhead @15%    1877.16
 Total rate  For 10cum 14391.56
 Total rate  For 1cum 1439.16

2 thoughts on “1. Rubble soling rate analysis: (Rate Analysis for Rubble soling)”

  1. This paragraph presents clear idea in support
    of the new viewers of blogging, that in fact how to do blogging and site-building.

Leave a Reply