The Rate Analysis for plinth filling is as follows,
Item Details: Filling in plinth with brought out Murum
Quantity Assumed: 10cu-m
Rate Assumed:
- Murum: 425 Rs per Cum
- Labour charges: 375Rs per Cum
Item No. | Item | Explaination | Quantity | Unit | Rate/unit | Amount |
A | Material | |||||
1 | Murum | 10 cum + 2cum | 12 | cum | 425 | 5100 |
(Add 20% compaction factor) | ||||||
Total of A | 5100 | |||||
B | Labour charges | 10 | no | 375 | 3750 | |
C | Wastage @ 5% | 255 | ||||
D | Plant & machinery @ 1% | 51 | ||||
E | Water & electricity including curing @ 2% | 102 | ||||
Total | 9258 | |||||
F | Add for profit & Overhead @15% | 1388.7 | ||||
Total rate | For 10cum | 10646.7 | ||||
Total rate | For 1cum | 1064.67 |